SR 44 widening, Phase II

Widen this section of SR 44 to four lanes with a divided median and bicycle accommodation, build a roundabout at Richland Connector, widen the Richland Creek bridge and replace the Little Creek culvert with two bridges.

Record date
November 5, 2026
Place
SR 44 from north of Carey Station Road to about three-quarters of a mile south of King Drive
Parcel
Transportation corridor · not parcel-specific
Authority
Georgia Department of Transportation
Stage
Under construction
Status
11.70% complete · official status observed November 5
What the record describes
Widen this section of SR 44 to four lanes with a divided median and bicycle accommodation, build a roundabout at Richland Connector, widen the Richland Creek bridge and replace the Little Creek culvert with two bridges.
Next evidence to look for
Track GDOT's reported completion percentage, schedule changes and construction records. The current completion date shown by GDOT is August 31, 2030; it is a current project schedule, not a guarantee or forecast by this archive.

Latest GDOT status

Checked 2026-11-24. Under Construction · 11.70% complete.

Current scheduled completion
2030-08-31
Actual completion
Not posted

See this activity in the development register. Source-linked entry. A match to another development has not been established..