Commercial permits
22 selected permits from May to September 2026 name 10 businesses and report $58,006,500 in declared value across 243,555 reported square feet.
A permit records authorization. Declared valuation measures reported construction value. Opening, licensure, public spending and final construction are separate facts.
| Date | Permit | Work | Business named | Declared value | Square feet | Source |
|---|---|---|---|---|---|---|
| 2026-08-26 | 20261441 | Addition at St. Mary's | St. Mary's | $33,000,000 | 50,000 | Original record |
| 2026-08-21 | 20261394 | Comfort Station - Front 9 - The Hideaway Golf Course | The Hideaway Golf Course | $300,000 | 1,373 | Original record |
| 2026-08-21 | 20261395 | Comfort Station - Back 9 - The Hideaway Golf Course | The Hideaway Golf Course | $200,000 | 570 | Original record |
| 2026-08-12 | 20261335 | 1 Cart Bridge and 1 Walking Bridge - 40x13x2 and 30x6x2 - Holes 13 & 14 - The Hideaway Golf Course | The Hideaway Golf Course | $200,000 | 1,400 | Original record |
| 2026-08-05 | 20261299 | 4 Restrooms - Phase II Frey Moss Manufacturing Facility - (State Approved) | Frey-Moss Structures | $200,000 | 480 | Original record |
| 2026-08-04 | 20261298 | (2) 500 sq. ft. Modular Office/Toolroom Structures - Phase II Frey Moss Manufacturing Facility | Frey-Moss Structures | $200,000 | 1,000 | Original record |
| 2026-07-29 | 20261277 | Fenmoor #3 - Short Course - Office/Maintenance Building | Not named | $1,400,000 | 6,855 | Original record |
| 2026-07-09 | 20261174 | Remodel Interior of Existing Space for New Business - Souper Jenny | Souper Jenny | $40,000 | 2,934 | Original record |
| 2026-06-16 | 20261074 | Antenna upgrades to an existing cell tower | AT&T | $25,000 | 308 | Original record |
| 2026-06-15 | 20261070 | Storage Building at Ritz Carlton Lodge | Ritz Carlton Lodge | $100,000 | 1,200 | Original record |
| 2026-06-09 | 20261005 | Frey-Moss Manufacturing Facility - Phase II | Frey-Moss Structures | $3,900,000 | 70,420 | Original record |
| 2026-06-08 | 20261004 | Athens Orthopedic Clinic - X-Ray Renovation | Athens Orthopedic Clinic | $185,000 | 2,770 | Original record |
| 2026-05-20 | 20260917 | Shred house wall and steel structure rebuild | Novelis | $1,036,500 | 7,425 | Original record |
| 2026-05-18 | 20260886 | Warehouse storage building | Amazon | $15,000,000 | 76,944 | Original record |
| 2026-05-12 | 20260851 | Retaining wall associated with Amazon project | Amazon | $35,000 | 0 | Original record |
| 2026-05-01 | 20260805 | Golf-course maintenance and office building | Not named | $1,400,000 | 13,040 | Original record |
| 2026-09-25 | 20261638 | Bluffs Phase II clubhouse | Not named | $300,000 | 1,849 | Original record |
| 2026-09-24 | 20261629 | Commercial interior build-out for lessee Academy Lock & Key | Academy Lock & Key | $250,000 | 3,200 | Original record |
| 2026-09-17 | 20261600 | Phase II amenity pavilion/cabana | Not named | $40,000 | 720 | Original record |
| 2026-09-17 | 20261599 | Phase II community mail kiosk | Not named | $70,000 | 515 | Original record |
| 2026-09-09 | 20261539 | Golf-course pavilion | Not named | $100,000 | 552 | Original record |
| 2026-09-01 | 20261491 | Existing cell-tower maintenance and repairs | Not named | $25,000 | 0 | Original record |
Development-related public awards
9 selected award records total $1,063,870 where amounts are stated. A payee was named in 6 records.
Award records describe decisions. Payment and delivery require separate evidence. Unknown amounts are excluded from the sum.
| Date | Project | Payee | Amount stated | Source |
|---|---|---|---|---|
| 2025-03-11 | Airport obstruction clearing and fencing | Complete Land Services, LLC | Not stated | Original record |
| 2025-06-10 | Airport avigation-easement acquisition services amendment | Holt Consulting Company, LLC | Not stated | Original record |
| 2024-02-13 | Greene County detention-center renovation | Dublin Construction Company | Not stated | Original record |
| 2024-11-12 | Senior Center expansion preliminary architectural report | McCall & Associates | $0 | Original record |
| 2024-06-11 | Road bridge improvement work | Not stated | $574,625 | Original record |
| 2023-06-13 | Land-development regulation revisions | Hatley Plans, LLC | Not stated | Original record |
| 2023-04-11 | Bridge and guardrail inspections and bid documents | Pavement Preservation Techniques | $20,000 | Original record |
| 2021-12-14 | County Annex parking-lot resurfacing | Not stated | $185,975 | Original record |
| 2021-12-14 | Administration building HVAC replacement | Not stated | $283,270 | Original record |